Start here: Buying a former factory or dry-cleaning site does not, by itself, trigger a soil investigation. Check what substances were used, the facility’s regulatory history, any existing designation and the works you plan. Absence from the register is not a clean bill of health.
For investors in mainland China and Taiwan acquiring Japanese business land, factories or former dry-cleaner sites, and their local advisers (accountants and lawyers), this organises how to check soil-contamination risk in pre-purchase due diligence (DD), from the provisions of the Soil Contamination Countermeasures Act (Act No. 53 of 2002) and materials of the Ministry of the Environment. Yotsuba Real Estate Co., Ltd. (四葉不動産株式会社; Real Estate Brokerage) handles the property survey, brokerage and important-matters explanation (by a real estate transaction specialist). We do not handle the soil investigation itself or the determination of contamination; we go only as far as organising information. See also what Chinese-speaking buyers watch in the important-matters explanation of investment property, the seller's side of soil contamination on former factory and warehouse sites in soil contamination and sale of former factory and warehouse sites, and working with local professionals on Japanese property. For investment and business property, see investment and commercial real estate consultations.
Why is the former site of a factory or dry cleaner at higher risk of soil contamination?
The "designated hazardous substances" under the Soil Contamination Countermeasures Act are substances such as lead, arsenic and trichloroethylene, designated by Cabinet Order (Art. 1 of the Enforcement Order) as those that may cause harm to human health through their presence in soil (Art. 2(1) of the Act). Dry cleaners have historically used chlorinated organic solvents such as tetrachloroethylene in dry cleaning, and factories have handled heavy metals and solvents in plating and metalworking; the former sites of facilities that manufactured, used or treated such substances are categorically more likely to retain designated hazardous substances in the soil.
Check the designation register against the seller’s records of facility operation and closure and any previous investigation reports. A site that is not listed is not the same as one that was investigated with negative findings. A designated investigation body carries out the statutory field investigation and evaluates the samples.
| Entry point of risk | Buyer's check | Whom to ask |
|---|---|---|
| Past use | History as a specified facility using hazardous substances | Prefecture (registry) / seller |
| Statutory area designation | Area Requiring Action or Requiring Notification | Prefecture / municipality (ledger) |
| Actual soil condition | Concentration of designated hazardous substances | Designated investigation body |
When does the investigation duty under the Act arise?
When use of a legally specified facility using hazardous substances ends, the owner or other responsible party must generally commission a designated investigator and report the results to the competent authority (Soil Contamination Countermeasures Act, Art. 3(1)). The authority may confirm that, under the proposed use, there is no risk to human health; investigation is then deferred while those conditions hold. For qualifying works affecting at least 900 m² on land with that confirmation, the owner or other responsible party must notify the authority in advance and arrange an investigation and report as ordered (Art. 3(7)–(8)). This is not the separate 30-day procedure below.
Article 4 generally requires advance notice for an alteration of 3,000 m² or more. The threshold is 900 m² on factory or business premises with a specified facility using hazardous substances, and on former premises of such a facility where neither the Article 3 investigation report has been filed nor a deferral has been confirmed (Enforcement Regulation, Article 22). For covered work the person undertaking it gives at least 30 days’ notice. Notice does not in itself trigger an investigation: if the statutory criteria for possible contamination are met, the authority may direct the owner or other statutory landholder to have the land investigated (Article 4(1), (3)). Article 5 separately permits an investigation order where the statutory health-risk criteria are met.
| Situation | Legal basis | Procedure to check |
|---|---|---|
| Discontinuation of a specified facility using hazardous substances | Art. 3(1) of the Act | Check the investigation/report history at acquisition |
| Qualifying works of at least 900 m² on land with an Art. 3 deferral | Art. 3(7)–(8) | Advance notification by the owner or other responsible party; investigation and report as ordered |
| Other qualifying changes to land | Art. 4(1), (3); Regulation Art. 22 | Generally 3,000 m² or more; 900 m² or more at specified sites. Notify at least 30 days before work; an investigation order is separate |
| Governor's investigation order | Art. 5(1) | Land at risk of harm to health |
How does an area designation as Area Requiring Action or Requiring Notification affect the sale?
Land that exceeds the contamination standard and presents a risk to health is designated an Area Requiring Action (Article 6). The prefectural governor or other competent authority identifies the measures required and the reasons for them, and directs the recipient to submit a response plan (Article 7). Alterations to the land are generally prohibited (Article 9). If the standard is exceeded but the statutory health risk is not found, the land is designated an Area Requiring Notification for Changes of Character (Article 11). A person planning work covered by Article 12 must generally give notice at least 14 days before starting. Specified routine maintenance and minor works are among the exceptions; emergency works after a disaster, for example, must be reported afterwards.
Match the lot number and designated area against the competent authority’s register. A designation may cover only part of the property: compare its map with the planned works. Once the affected area and restrictions are clear, evaluate their impact on the timetable and financing.
| Type of area | Basis of designation | Main regulation |
|---|---|---|
| Area Requiring Action | Article 6(1) | Direction to submit a response plan (Article 7); land alterations generally prohibited (Article 9) |
| Area Requiring Notification for Changes of Character | Article 11(1) | For covered work, generally give notice at least 14 days in advance; statutory exceptions apply (Article 12) |
| How to confirm the area | Prefecture / municipality ledger | Inquire into the history of designation and release |
How do I get estimates for investigations, remedial work and timing?
For a useful estimate, compile the records of past uses and identify the substances and areas to be investigated. Ask for separate costs for field sampling and analysis and for any remedial works that may prove necessary. Ask when a report will be available, not only when drilling can start.
Before signing, agree who will pay for testing and for any remedial work. Separately, decide what happens to the price, closing or handover if the results affect the proposed use. These contractual terms do not change who receives a direction from the authority. Consult a lawyer about disputed liability and a tax accountant about the tax treatment.
Have a question about your situation?
Tell us about your property search or plans to sell.
| Stage | Content | Who is mainly in charge |
|---|---|---|
| History investigation | Past use and facility history | Designated investigation body / seller materials |
| Preliminary and detailed investigation | Concentration and range of designated hazardous substances | Designated investigation body |
| Measures | Excavation and removal, in-situ purification, capping, etc. | Remediation contractor |
| Contractual arrangement | Cost burden; non-conformity clause | Broker (important-matters explanation, contract) |
Who handles what, and how far (separate engagement)?
DD on a former site involving soil contamination involves several specialists. Yotsuba Real Estate Co., Ltd. handles the property survey, brokerage and important-matters explanation (by a real estate transaction specialist). Whether it is an Area Requiring Action or Requiring Notification — the presence of an area designation — is organised within the important-matters explanation as a restriction under laws under Art. 35(1)(ii) of the Real Estate Brokerage Act (Act No. 176 of 1952). On the other hand, the investigation of the contamination state by soil sampling and analysis, and the determination of the presence and degree of contamination, exceed the scope of the important-matters explanation and are not handled.
The soil investigation lies with a designated investigation body designated by the Minister of the Environment or the prefectural governor; administrative procedures such as the Art. 3 and Art. 4 notifications and responding to area designation lie with an administrative scrivener; tax on removal cost and acquisition (including withholding where the seller is a non-resident) with a tax accountant; and disputes over contamination, such as damages and non-conformity, with a lawyer. These are independent entities from us, engaged separately for each service. We act as a single point of contact to each specialist, but engagement, invoicing and payment are done directly by each, with no referral or lead-transfer fees. Supporting document provision in traditional and simplified Chinese is available, organising the uniquely Japanese pre-purchase check of soil contamination in your own language.
| Who | Role |
|---|---|
| Yotsuba Real Estate Co., Ltd. (brokerage) | Property survey, brokerage, important-matters explanation (restrictions under laws) |
| Designated investigation body | Soil investigation (sampling and analysis) |
| Yotsuba Administrative Scrivener Office | Art. 3 / Art. 4 notifications; procedures for area designation |
| Tax accountant | Tax on removal cost and acquisition (incl. non-resident withholding) |
| Lawyer | Disputes over contamination (damages, non-conformity) |
Frequently asked questions
Q. Where can I find out whether a former site is subject to the Act's investigation duty?
A. Ask the seller for the facility's operating and closure records and any Article 3 report or written deferral. Show the planned works to the local authority. Qualifying works of at least 900 m² on land with a confirmed deferral require advance notice under Article 3. For Article 4 works, notice is due at least 30 days before starting; the threshold is generally 3,000 m², or 900 m² at specified sites. Neither a sale nor the site area alone decides whether an investigation is required.
Q. If the land is designated an Area Requiring Action or Requiring Notification, must I not buy?
A. Designation alone does not prohibit a sale. For an Area Requiring Action, check the response-plan direction and restrictions on building works. For an Area Requiring Notification for Changes of Character, check whether your project needs at least 14 days’ advance notice or falls within a statutory exception. Compare the authority’s map with the proposed works before budgeting for time and cost.
Q. Will the broker investigate whether the soil is contaminated?
A. The broker checks the land’s designation and explains relevant information, such as past investigation reports provided by the seller. This is different from sampling and analysing soil. A statutory on-site investigation must be handled by a designated investigation body.
Q. Who bears the cost of investigation and measures, the seller or the buyer?
A. The sale contract can allocate investigation and remedial costs between seller and buyer. It cannot change who must submit a plan under Article 7: normally the owner or other statutory landholder. If another polluter is identified, it is appropriate for that party to act and the landholder does not object, the direction goes to the polluter. Under Article 8, a landholder who was directed to act and carried out the measures may recover qualifying costs of preparing or amending the plan and implementing the measures from another responsible polluter, up to the statutory cap. This is not a general right to recover pre-purchase investigation costs.
Primary sources
- Soil Contamination Countermeasures Act (e-Gov, Japanese): Articles 2–5 (definitions, investigation and notice), 6–9 (designation, plan submission, cost recovery and restrictions), and 11–12 (notifiable work, timing and exceptions). Act version effective 1 July 2026 (Act No. 22 of 2026); Enforcement Regulation, Article 22, version effective the same day (Ministry of the Environment Ordinance No. 19 of 2026).
- Ministry of the Environment: guidance on Article 4 notice and area thresholds (Japanese).
- Japan’s Ministry of the Environment: guidelines and manuals on investigations and measures and designated investigation bodies (Japanese).
- Real Estate Brokerage Act, Article 35(1)(ii) (version effective 1 April 2026, Act No. 68 of 2025); Enforcement Order, Article 3(1)(lvii) lists the restrictions in Articles 9 and 12(1) and (3) of the Soil Contamination Countermeasures Act (Japanese).
Sources checked: 25 November 2026. For a particular site, take the closure record, any written deferral, investigation reports and works plans to the competent authority and a designated investigator.
This article provides general information and does not present individual legal conclusions, a determination of contamination, or tax conclusions. Confirmation by the competent authorities and qualified professionals is required. Yotsuba Real Estate Co., Ltd. (四葉不動産株式会社), 四葉行政書士事務所, 四葉社会保険労務士事務所 and other specialists (designated investigation body, remediation contractor, tax accountant, lawyer) are independent entities, engaged separately for each service. We proceed by direct contract, direct invoice and direct payment; no referral or lead-transfer fees are exchanged. The initial property consultation is free; confirm each professional's scope and fees with that provider.
Author
Joji Uramatsu (浦松 丈二), real estate transaction specialist (Tokyo Governor registration No. 293544) and administrative scrivener (registration No. 25087022); representative director of Yotsuba Real Estate Co., Ltd. (四葉不動産株式会社; Real Estate Brokerage, Tokyo Governor (1) No. 113304) and representative of 四葉行政書士事務所. In Kohinata, Bunkyo-ku, Tokyo, about five minutes' walk from Myogadani Station. Supporting document provision in traditional and simplified Chinese, he organises the pre-purchase check of former factory and dry-cleaner sites — property at high risk of soil contamination — for Chinese-speaking buyers and local professionals in their own language. He keeps the explanation of restrictions under laws within the real estate transaction specialist's scope, referring the soil investigation to a designated investigation body, notifications to an administrative scrivener, and tax and disputes to the respective providers. Author profile.
Related Articles
- 2026.11.25Investment & business property
A Japanese \"no-rebuild\" property reviewed in Chinese: the frontage-road duty and due diligence on Article 43
- 2026.11.24Investment & business property
For Chinese-speaking buyers: due diligence on a property \"with disclosure matters\" (psychological defect)
- 2026.11.24Investment & business property
Buying land with an unfixed boundary: how to check the parcel boundary, ownership boundary and area correction
Feel free to reach out for a consultation
Questions about our column articles are also welcome.
It's fine to start with just one line: “What should I do with this?”
Our representative replies to you personally, and if a property matches your needs, we will introduce it via LINE.
LINE connects you directly to our representative, Joji Uramatsu. Messages are accepted 24/7 and answered in order.
5 min walk from Myogadani Sta. (Tokyo Metro Marunouchi Line)|10:00–18:00 (Closed Tue & Wed)